Spain Base Load Case Study
Temporary Power to Support the Grid
An important power plant in Melilla, Spain
was installing new generators at their site. During the
installation process, sizeable losses of power were expected.
Power Plant Rental
Aggreko initially installed 5 MW of power to supply the
necessary back up power. During the installation period, power
demand in the area drastically increased. Aggreko immediately
increased the temporary power supply to 11 MW to compensate for the
change in power demand. The customer’s grid base load station was
fully manned by Aggreko for three years.
Temporary Power
Aggreko’s temporary power supply allowed the
grid station to meet demand without any disruption. Aggreko’s
reliability, quick response and flexibility to provide additional
equipment successfully maintained operations for the plant.